Trimont Feed Mill Slip Form Process Begins

Just after 8 am this morning, the McCormick Construction crew began the continuous concrete pour of the slip forms at the new feed mill in Trimont. Work will be non-stop with rotating shifts until the 160+ foot pour is complete.

The process is complex as all concrete is poured into funneled chutes by hand with a wheelbarrow delivery. Overall, there are 53 funnels for the continuous concrete pour, with 27 specifically for the outside walls.

The slip will move upward approximately 10 inches per hour, raising the platform along with it. Completion of the mill should take 9 to 10 days, and once finished, the pour on the silo will begin.

Watch the progress on our website by visiting: https://bit.ly/3smBrQI

Cement truck delivery

Cement truck delivery

On top of the platform.

On top of the platform.

Beginning the cement loading process.

Beginning the cement loading process.

Dsc 5179

Pouring cement for the outside walls.

Pouring cement for the outside walls.

Pouring cement for the outside walls.

View of the lower level

View of the lower level

View News